I'm building a house in Murrumbateman NSW to Passivhaus principles, with the thinking that a building is just infrastructure that's harder to roll back. So: sensors cast into the slab, drone surveys flown and processed as separate epochs, everything modelled in 3D. The rest of it has been a self-taught crash course in construction — reading Australian Standards, learning what a certifier actually needs, managing supply. Documenting all of it here.
Michael Pasqualone
Dad, husband, owner, co-project manager & an IT guy

As Built Documentation & Drone Surveys
- Aug 18, 2026
- Documentation , Survey , Technology
What level of documentation I currently have, and some lessons with surveying.
Read More
The Slab
- Aug 13, 2026
- Slab , Insulation , Hydronics , Heating
All the work to get drainage, hydronic heating, slab insulation in, and pour day - how our slab came together after weeks of work.
Read More
Site Cut & Miscalculations
- Jul 13, 2026
- Earthmoving
How hard could it be to calculate how much soil will be left over?
Read More
DA Application - Take 2
- Jun 9, 2025
- Council
My second, and accepted attempt at DA with fixes to septic plans, site plan and other additional information requested by Council.
Read More
DA Application - Take 1
- Apr 1, 2025
- Council
My first ever attempt at submitting a Development Application.
Read More
The Dying Tree
- Dec 13, 2020
- Landscaping , Council
We recently had to remove a dead tree from our property after confirming with two arborists that it was beyond saving. While it was a tough decision, the tree posed safety risks and couldn’t be revived.
Read More