Budget

I used 3 main methods to cost and budget our build; I’ve will also be creating a detailed blog post about this topic.

  • Rawlinsons Construction Cost Guide
  • Retail and online pricing, plus my experience I have with technology supply chains
  • Quote from our builder, broken down into 46 categories.

As a general rule, we’ve realistically budgeted this build — I’d rather be pleasantly surprised when something comes in cheaper than shocked by how expensive it actually turns out to be. I won’t publically put our budget here.

The charts and data on this page will update nightly at 10.42pm via a Github scheduled Action, pulling data from Pocketsmith.

Current Budget Status

$21,892 (underbudget)

Savings Target

After 1 of 5 stage completions, my target is a $175,000 savings compared to my original budget.

History

Tip: A positive (green line) number represents a budget savings, and a negative number (red line) is an overspend.

---
config:
    xyChart:
        width: 900
        height: 600
        titlePadding: 20
    themeVariables:
        xyChart:
            backgroundColor: '__CHART_BG__'
            plotColorPalette: '__CHART_LINE__'
---
xychart
  title "Build Underspend/Overspend Tracking History"
  x-axis ["2026-08-21", "2026-08-22", "2026-08-23", "2026-08-24", "2026-08-25", "2026-08-26", "2026-08-27", "2026-08-28", "Latest"]
  y-axis "Dollars" 0 --> 127500
  line "savings" [127500 "$127,500", 55606 "$55,606", 55606 "$55,606", 43663 "$43,663", 22400 "$22,400", 22400 "$22,400", 22400 "$22,400", 21892 "$21,892", 21892 "$21,892"]

Detailed Budget Breakdown

Legend:

  • ✔️ = Final spend, no more to spend.
  • 💲 = More to spend.
  • 🤞 = Possibly more to spend, not sure yet, but “fingers-crossed” likely to be under budget still.

Council & Pre-Start

ItemBudgetActual SpendStatusNotes
DA Fees$10,000$12,256✔️This came in higher due to NSW Long Service Levy (Building and construction) that I only found out about after our DA was approved.
Certifier Fees$4,000$2,970✔️
Surveyor$4,000$2,200✔️Cash job brought this in much cheaper, also did several GCP targets for me for drone usage
Insurance$10,000$6,659✔️I initially budgeted this based on a pure guess

Foundation & Earthworks

ItemBudgetActual SpendFinalisedNotes
Site Cut$20,000$11,396🤞We saved heaps in this department because I found a local, had a game plan for them and I ensured we didn’t need to move any cut materials offsite.
Drainage, Stormwater$15,000$14,600✔️This line item was the very first invoice I received from a trade, and boom! I was pretty much bang on
Underslab Insulation$7,500$3,507✔️I priced on retail, once I setup trade supply - it came in heaps cheaper. I also bought with 20% wastage, and had heaps left over.
Slab-edge Insulation$7,500Not purchased yet, but will be way cheaper than budgeted
Hydronic Heating Slab Provision$16,000$9,512💲Includes pipes, 2x manifolds, floor sensors
Slab Sensors & Monitors$1,000$240✔️I installed 6x DS18B20 temp sensors

Electrical & Data

ItemBudgetActual SpendFinalisedNotes
Conduit & Electrical Pre-Provision$3,000$2,776💲I did all the conduit myself as electrican was happy for me to do it

Framing, Trusses and Roof

ItemBudgetActual SpendFinalisedNotes
140mm External & 90mm Internal Frames
Roof Trusses
Stuctrual Steel & Timber
Rigid Insulation Panels
Sarking & Tapes
Framing InsulationFoam Gaskets, Tapes, Sealants,etc

Windows, Doors & External Thermals & Weathertightness

ItemBudgetActual SpendFinalisedNotes
Thermally-broken Windows$120,000$34,600✔️I will create an entire blog post just for this line-item, but I managed to get a recommendation and introduction from a local retired architect who has built a passivehaus himself in Hume for thermally broken, double glazed, warm-edge, imported European tilt and turn windows.
Thermally-broken Bifold Doors
External Doors
Internal Doors

Lockup Stage

ItemBudgetActual SpendFinalisedNotes

Fixings Stage

ItemBudgetActual SpendFinalisedNotes